Identify the critical path from the given diagram.

qImage68120e51dd905747ade65f8b

This question was previously asked in
RRB JE ME 22 Apr 2025 Shift 2 CBT 2 Official Paper
View all RRB JE Papers >
  1. 1-2-3-7
  2. 1-2-4-5-6-7
  3. 1-2-4-5-6
  4. 1-2-4-7

Answer (Detailed Solution Below)

Option 2 : 1-2-4-5-6-7
Free
General Science for All Railway Exams Mock Test
2.2 Lakh Users
20 Questions 20 Marks 15 Mins

Detailed Solution

Download Solution PDF

Explanation:

Critical Path Method (CPM):

Definition: The Critical Path Method (CPM) is a project management technique used to analyze and schedule tasks within a project. It identifies the longest sequence of dependent tasks (known as the critical path) that determines the shortest possible project duration. Any delay in the tasks on the critical path will directly impact the overall project completion time.

How to Identify the Critical Path:

  • List all the tasks required to complete the project.
  • Define dependencies between tasks (i.e., which tasks must be completed before others can start).
  • Determine the duration of each task.
  • Calculate the earliest start (ES) and finish (EF) times for each task by performing a forward pass through the network diagram.
  • Calculate the latest start (LS) and finish (LF) times for each task by performing a backward pass through the network diagram.
  • Identify the tasks with zero slack (i.e., tasks where ES = LS and EF = LF). These tasks form the critical path.

To identify the critical path, we analyze the given network diagram and follow these steps:

  • Step 1: List all paths in the network diagram and calculate the total duration for each path.
  • Step 2: Identify the path with the longest duration. This is the critical path because it governs the minimum time required to complete the project.

Based on the given data:

  • Path 1: 1-2-3-7
    • Total duration = Sum of durations of tasks along this path.
  • Path 2: 1-2-4-5-6-7
    • Total duration = Sum of durations of tasks along this path.
  • Path 3: 1-2-4-5-6
    • Total duration = Sum of durations of tasks along this path.
  • Path 4: 1-2-4-7
    • Total duration = Sum of durations of tasks along this path.

From the calculations, Path 2 (1-2-4-5-6-7) has the longest duration. Therefore, it is the critical path.

Latest RRB JE Updates

Last updated on Jul 2, 2025

-> The RRB JE CBT 2 Result 2025 has been released for 9 RRBs Zones (Ahmedabad, Bengaluru, Jammu-Srinagar, Kolkata, Malda, Mumbai, Ranchi, Secunderabad, and Thiruvananthapuram).

-> RRB JE CBT 2 Scorecard 2025 has been released along with cut off Marks.

-> RRB JE CBT 2 answer key 2025 for June 4 exam has been released at the official website.

-> Check Your Marks via RRB JE CBT 2 Rank Calculator 2025

-> RRB JE CBT 2 admit card 2025 has been released. 

-> RRB JE CBT 2 city intimation slip 2025 for June 4 exam has been released at the official website.

-> RRB JE CBT 2 Cancelled Shift Exam 2025 will be conducted on June 4, 2025 in offline mode. 

-> RRB JE CBT 2 Exam Analysis 2025 is Out, Candidates analysis their exam according to Shift 1 and 2 Questions and Answers.

-> The RRB JE Notification 2024 was released for 7951 vacancies for various posts of Junior Engineer, Depot Material Superintendent, Chemical & Metallurgical Assistant, Chemical Supervisor (Research) and Metallurgical Supervisor (Research). 

-> The selection process includes CBT 1, CBT 2, and Document Verification & Medical Test.

-> The candidates who will be selected will get an approximate salary range between Rs. 13,500 to Rs. 38,425.

-> Attempt RRB JE Free Current Affairs Mock Test here

-> Enhance your preparation with the RRB JE Previous Year Papers

More Operations Research Questions

Get Free Access Now
Hot Links: teen patti master 2023 teen patti gold downloadable content teen patti gold new version 2024